representation to WBRERA for cancellation of the Project

 

Date : 4th day of July’ 2022

To,

The West Bengal Real Estate Regulatory Authority, having its Office at Calcutta Greens Commercial Complex, 1st Floor, 1050/2, Survey Park, Santoshpur, Kolkata – 700075.

Ref.: HIRA/P/SOU/2018/000305 “DEVALOKE SONAR CITY” Simultala, Sonarpur Station Road, Holding no. 1117, under Ward no. 8, Rajpur Sonarpur Municipality, Post Office – Ramkrishna Pally, Police Station – Narendrapur, District South 24 Parganas.

Subject : Cancellation of the approval of Project Work “DEVALOKE SONAR CITY” Simultala, Sonarpur Station Road, Holding no. 1117, under Ward no. 8, Rajpur Sonarpur Municipality, Post Office – Ramkrishna Pally, Police Station – Narendrapur, District South 24 Parganas accorded to M/s. Devaloke Developers Limited, having its Registered Office at Premises being no. 82, Garia Main Road, Mahamayatala, Post Office – Garia, Police Station – Naredrapur, Kolkata - 700084, and being represented by its Director namely one Sukanta Kundu, Swarup Kundu, Shankar Kundu, and Antara Guha Kundu,  for their illegal and unauthorized construction in violation Title Suit no. 206 of 2022.

Sir/s,

I, Sri Kamal Sardar, Son of Year Ali Sardar, residing at Jagannathpur Bhangi Para, Post Office – Ramkrishna Pally, Police Station – Narendrapur, Kolkata – 700150, District South 24 Parganas, should like to state as follows;

1.   That I am the bonafide Owner of a Plot of Land measuring about 29 Decimal Land comprising of C.S. Dag no. 438 corresponding to R.S. Dag no. 438, corresponding to L.R. Dag no. 480 of C.S. Khatian no. 120, corresponding to R.S. Khatian no. 452, under Mouza Jaganathpur, Police Station – Narendrapur, District – South 24 Parganas.

 

2.   That I have never transferred my said property to anybody else. One Devaloke Developers Limited, having its Registered Office at Premises being no. 82, Garia Main Road, Mahamayatala, Post Office – Garia, Police Station – Naredrapur, Kolkata - 700084, and being represented by its Director namely one Sukanta Kundu, Swarup Kundu, Shankar Kundu, and Antara Guha Kundu, has started construction work encircling a huge area where under my said property situated.

 

3.   That kindly take note, I am in possession of my said property; but the said developer company twice tried to dispossess me from my property.  On the fear of dispossession, I made Written Complaint before the local Police Station.

 

4.   I have already filed a Civil Suit being T.S. no. 112 of 2022, before the Learned 2nd Civil Judge ( Senior Division) Baruipur, South 24 Parganas against the said developer, which is still pending and wherein by order dated 08-03-2022, the Learned Court 2nd Civil Judge ( Senior Division ) Baruipur, South 24 Parganas, has been pleased to allow the prayer of injunction and the parties therein have been ordered to maintain “status quo”. The said order of injunction has been extended from time to time and same is still in force.

 

5.   That I have already made representation before the concerned Municipality for cancellation of the sanctioned building plan, and for stoppage of ongoing construction work.

 

6.   That the said Developer in violation of the Title Suit no. 112 of 2022, is still continuing with the construction work.

 

7.   That reportedly the concerned Municipality has sanctioned the building plan in suit plot of land which belongs to me. I never gave them no objection for such construction on my own land. Pursuant to the said sanction, you have also approved the Project Work, in favour of the said Developer. Since the said Developer is making illegal and unauthorized construction as such you must withdraw your approval for continuation of the said Project Work.

 

In the circumstance I request you to cancel the Project namely “DEVALOKE SONAR CITY” already sanctioned in favour of the said developer and take necessary steps, for stopping construction work, which the said developer, is continuing.

 

In the circumstance I request you to take necessary steps restraining the said developer in carrying on further construction.

 

This is for your information and immediate action.

 

Thanking you,

 

Yours’ faithfully,

 

 

Kamal Sardar,

Son of Year Ali Sardar,

Jagannathpur Bhangi Para,

Post Office – Ramkrishna Pally,

Police Station – Narendrapur,

Kolkata – 700150,

District South 24 Parganas

 

Copy to ;

The Designated Authority,

The West Bengal Real Estate Regulatory Authority, having its Office at Calcutta Greens Commercial Complex, 1st Floor, 1050/2, Survey Park, Santoshpur, Kolkata – 700075.

{ for information and necessary action }