Before
the Hon’ble State Consumer Disputes Redressal Commission, West Bengal, at
premises being no. 11A, Mirza Ghalib Street, Kolkata – 700 087.
Complaint Case no.
CC/554/2017.
In
the matter of
:-
Manoj
Dutta,
……
Petitioner
-
Versus
–
N. K. Constructions
and others,
………Opposite
Parties
BRIEF NOTES OF
ARGUMENT
ON BEHALF OF THE
PETITIONER
MANOJ DUTTA
Facts :
- The
Complainant being in dire need of a residential accommodation, had entered
into an agreement dated 16.10.2015, with the developer for a self
contained flat being no. MMD-15D, Block –C, with a super built up area of
744 sq. ft. East side of the building named Manisha Apartment along with a
car parking space against a total consideration of Rs. 19,71,600/- and Rs.
55,000/- for electric and maintenance charges.
- The
Complainant had paid such consideration for the subjected flat and charges
towards electric and maintenance. The schedule flat was promised to be
handed over, by the developer, in habitable condition within 15 months
from the date of the agreement i.e. 16/10/2015, within 16/03/2017.
- The
Complainant duly acted in terms of the agreement and made payment strictly
as per the schedule. Thus it is evident on the face of record that the
complainant had performed on his part, therefore the developer is legally
bound to render appropriate services, interalia, strictly as per the
agreement dated 16/10/2015, by constructing and delivering possession of
the residential flat to the complainant upon completion of the same by
16/03/2017.
- The
Developer failed and neglected to perform in terms of the agreement and
complete the construction of the flat and handover the possession of the
same to the complainant being consumer as meant for the Consumer
Protection Act 2019, within schedule period on 16.03.2017.
- Since
October 2015, the Complainant time and again requested the Developer to
hand over the Possession of the said subjected flat within the stipulated
period. However, after receipt of the entire consideration amount, the
Developer showed no improvement in construction and development of the
said subjected flat and did not hand over the same within the stipulated
period, within 16.03.2017.
- The
Developer has taken a dilatory tactics to harass a bonafide consumer by
way of severe deficiency in service and unfair trade practice. The
developer is also enjoying the interest accrued on such consideration
money paid by the complainant in terms of the said agreement for sale.
- The
developer has received the entire consideration money as well as the
charges towards electricity and maintenance. The residential flat was to
constructed and possession delivered by 16.03.2017, however even after
lapse of almost one and half year the residential flat was not ready for
possession. The construction of the flat yet to be completed. The
developer has stated no reason for such inordinate delay and has further
failed and neglected to act in terms of the agreement to compensate the
complainant for such delay in possession. That apart the developer has
maintained a stoic silence against the eager query of the complainant,
while the cause of action runs from day to day.
- In
the given facts and circumstances, there is a deficiency in service on the
part of the developer and the complainant has suffered loss and damages
and as such he is entitled to appropriate relief as per provisions of the
Consumer Protection Act’ 2019.
During the proceeding
;
9.
On
receipt of notice, the Opposite Party no. 1, 2, 3 & 4, has appeared in the
present consumer proceeding. The opposite parties has submitted their written
version, cited as written version by the Opposite Party no. 1, 2, 3, & 4,
though there is no such averment has been given by the Opposite Party no.1,
that the Opposite Party no. 2,3, & 4, has ever been authorized him to give
such written version on their behalf also.
10. The said written
version of the opposite party no.1, is in very formal in nature based on denial
only. However the opposite party contended that the complainant what he has
stated in paragraph number 2, 3, 4, 5, 6, & 7, of the complaint case that
is correct. The opposite party no.1, even after admitting the facts and
contents and purports of the consumer complaint, failed to answer on
allegations raised by the petitioner, which are well founded and established.
11. The opposite party
no.1, did not produce any document, to show that the subjected flat at the
premises has ever delivered to the complainant by producing completion
certificate of the premises from concerned Civic Body, as well as the Letter of
Possession, So far.
12. The opposite party
no.1, obliged to state some additional facts to cover-up his deficiency in
services to the complainant, which are as follows;
Paragraph number 8 –
That this opposite parties humble stated that they had applied to West Bengal
State Electricity Distribution Company Limited (WBSEDCL) for sketching a new
line for service connection showing the premises from existing LV & MV
line. The said department had issued the notice to the Opposite Parties dated
26/10/2016 memo No. 1003519779/ APP RECT/01, and deposited @ Rs. 9,10,196/-
only dated 13/3/18 to WBSEDCL.
Paragraph number 9 –
That this Opposite Parties further stated herein that they did not give any
electric connection to their lot of flats because delay to connection with the
electric transformer after that the opposite parties have been going several
times but the WBSEDCL department did not give the said electric transformer of
the premises of the building for which the opposite parties could not give
connection to the flat holders of the building.
Paragraph number 10 –
That the Opposite Parties further stated herein that a lot of flat holders
could not complaint of the same because they knew the electric connection will
be delayed after long time for which they purchased a lot of flats of the
building. The petitioner in this case wrongly complained before the Learned
Court that’s why who wanted to know about this problem as such he purchased the
flat with consent of the opposite parties.
13. The Opposite Party
no.1, categorically stated in the Written Version in paragraph number 11, as
follows;
“That the Complainant
what he has stated in paragraph 2,3,4,5,6, &7 of complaint case that is
correct”.
14. The Opposite Parties consequentially
submitted their Evidence on affidavit wherein the Opposite Parties stated as
follows;
Paragraph number 9 –
That all the flat owners of the building i.e. Manisha Apartment are consuming
the electricity from that transformer as well as the lift is under construction
for the delay of delivering of the transformer from the concerned office of the
WBSEDCL. This is in the knowledge of all the flat holders including the
Petitioner.
Paragraph number 11 –
That the allegations of the petitioner are baseless as it is not our fault to
deliver him the facilities but due to the several times refusal and delay of
the concerned office of the WBSEDCL we could not provide them the facilities
but we have arranged a substitute procedure for consuming the electricity from
our other building and this secondary connection of electricity has been
provided to all the 34 flats including the petitioner’s flat of the said
building.
15. That it is pertinent
to mention that the opposite parties contentions as stated in their written
version, changed with further additional facts in respect to the lift and
concern to the Electricity connection, so, far. The facts apart from the
pleading of the opposite parties should not take on record, while weighing the
evidence placed by the Opposite Parties.
16. That while the
Complainant put forward the questionnaire on submissions of the Evidence on
Affidavit of the Opposite Parties. The Opposite Parties did not reply to the
specified questions given by the Complainant, and again submitted their written
contentions insist of reply to the questions of the complainant.
17. The Opposite Parties
are not even due diligent to contest the Consumer proceeding, which apparently
shows cause of their deficiency in services and unfair trade practices as meant
for in the Consumer Protection Act’ 2019.
Submissions :
18. The material facts placed by the Petitioner is
unchallenged.
19. The Documents relied on by the Petitioner, as (a)
List of Document submitted to Bank, (2) Receipt of Electric Transformer and
maintenance, (3) Sanctioned Letter received from Bank, (4) Copy of Letter
forwarded to NK Construction for handing over the Flat, (5) another copy of
letter forwarded to NK Construction for handing over of the flat, (6) Copy of
Deed of Sale, are sufficient to established the contents & purports of the
petitioner as stated in his petition of consumer complaint and his Evidence on
Affidavit.
20. In the given facts
that the subjected flat is still not completed. The agreed terms for completion
of the flat, has been violated by the opposite parties.
21. The facts and the
Documents placed by the Petitioner has not been rebutted by the Opposite
Parties.
22. In the given facts,
your petitioner is entitled well to get relief in terms of his prayer, placed
before the Hon’ble Commission.
Judicial references :
23. In the case of Saradamani Kandappan Vs. S.
Rajalakshmi & Ors., [ (2011) 12 SCC
18], the Honble Supreme Court has observed that as a general preposition of law
time is not essence of contract unless the parties to the contract intend
to make time an essential condition for performance of contract, by
expressly providing so or it can be inferred by necessary implication from
conduct of the parties. The Apex Court has appears to have said that the said
general presumption of law that time is not the essence of a contract that
is for sale of immovable properties needs to be revisited as time forms an
essential condition for the performance of contract in circumstances
of ever-increasing prices of real-estate property which are bound to
affect transactions of sale of immovable property. In our considered view,
the condition that time shall be the essence of this contract is an
essential condition applying to any clause in the Agreement where time is fixed.
24. The Judgment dated 31/07/2017
of the Honble National Commission in Consumer Complaints No. 1131 to 1140 of
2016 ( C.C. No. 1130/2016. Niru Kaushal & Anr. Vs. Unitech Ltd.)
and Judgment dated 06/05/2019 in Consumer case No. 1702/2016, [Shalab Nigam Vs. Orris Infrastructure and
3C Company (NCDRC)]. In the cases supra and in many other cases like
Complaint No. 347 of 2014, Swarn Talwar
and 2 Ors Vs.
Unitech Ltd. and other connected consumer complaints.
(Judgment dated 14/08/2015), Satish Kumar Pandey & Anr. Vs.
Unitech Ltd. and connected matters. (Judgment dated 08/06/2015), similar view
has been taken. it is observed as under:- It is an undisputed proposition of
law that ordinarily the parties are bound by the terms and conditions
of the contract voluntarily agreed by them and it is not for a Consumer
Forum or even a Court to revise the said terms. However, a term of a contract,
in my view will not be final and binding if it is shown that the consent to
the said term was not really voluntary but was given under a sort of
compulsion on account of the person giving consent being left with no other choice
or if the said term amounts to an unfair trade practice.
25. In the case of Kolkata
West International City Pvt. Ltd. Vs. Devasis Rudra [Civil Appeal No.
3182 of 2019 @ SLP (C) No(S). 1795 of 2017], the respondent had paid an amount
of Rs. 39,29,280/- in
No comments:
Post a Comment